SolAmerica 3 MW solar energy system, 243 Archer Road
Chili
Description
First one-year extensions of the final site plan approval and special use permit for a 3-megawatt solar farm, delayed by RG&E utility upgrade scheduling to 2028.
Impact summary
Construction now expected in early 2027 with energization tied to utility upgrades in 2028; town stands to gain over $800,000 under a pending benefit agreement.